ADKG-10 with valve skid
- Centralized supplier - transparent delivery boundaries, and obligations
- Unit protection thanks to reliable ARA with AUMA intelligent explosion-proof electric drives
- Compactness thanks to competent line-up solutions for the placement of ZRA and related systems
- Optimization and economy in the design and construction of a technological line, as a result
Basic information
The integrated solution – a basic unit with a skid of shut-off and control valves in a mounting frame: start-up, protection and bypass without stopping the main production line.
This solution was born in an effort to minimize the CAPEX and OPEX of our clients in both onshore and offshore projects. Thanks to the concept of a “centralized supplier”, the customer gets transparent delivery boundaries and obligations, and the use of a reliable valve skid with intelligent explosion-proof AUMA actuators ensures guaranteed protection of the unit against emergency situations.
Completed projects based on ADKG-10 with valve skid
Всего агрегатов: 12
ADKG-10 | Project | Customer | Quantity | Year |
---|---|---|---|---|
ADKG-10 | GP 16 SOG Pestsovaya area of the Urengoy Oil and Gas Condensate Field (OGCF) | LLC “Gazprom dobycha Urengoy” | 10 | 2008 |
ADKG-10 | Integrated Gas/condensate Processing Plant (IGPP) of Yurkharovsky OGCF | LLC “NOVATEK-YURKHAROVNEFTEGAZ” | 9 | 2008 |
ADKG-10 | IGPP 1B, 2B Zapolyarnoye OGCF | LLC “Gazprom dobycha Yamburg” | 7 | 2009 |
ADKG-10 | IGPP Nakhodkinskoye OGCF | LLC ”Lukoil Zapadnaya Sibir” | 4 | 2010 |
ADKG-10 | IGPP Bovanenkovskoye OGCF | LLC “Gazprom dobycha Nadym” | 40 | 2012 |
ADKG-10 | IGPP Kharvutinskoy ploshchadi Yamburgskovo OGCF | LLC “Gazprom dobycha Yamburg”м | 8 | 2012 |
ADKG-10 | IGPP Yurkharovskoye GCF | LLC “NOVATEK-YURKHAROVNEFTEGAZ” | 2 | 2013 |
ADKG-10 | SOG KS 42 Yarynskaya | ООО “Gazprom transgaz Ukhta” | 22 | 2014 |
ADKG-10 | IGPP Achimovskoye OGCF | PJSC "NOVATEK", JSC "Arktikgaz” | 4 | 2015 |
ADKG-10 | IGPP Samburgskoye OGCF | PJSC "NOVATEK", JSC "Arktikgaz” | 7 | 2016 |
ADKG-10 | IGPP Yaro-Yakhinsky OGCF | PJSC "NOVATEK", JSC "Arktikgaz” | 2 | 2016 |
ADKG-10 | UNTS at the Arslan IGPP | «ENTER Engineering Pte. Ltd. » | 2 | 2019 |